Wetlands and Conservation Commission Review

When work near wetlands, streams, or rivers needs Conservation Commission approval in Massachusetts, and how it can shape a project long before zoning does.

Last updated January 20, 2026

Wetlands review is one of the most common reasons a Massachusetts project takes longer, or changes shape, than expected. It runs separately from zoning, through the local Conservation Commission.

What triggers review

The Wetlands Protection Act (M.G.L. c. 131, § 40) and its regulations (310 CMR 10.00) protect wetlands, banks, floodplains, and other resource areas. Review is generally required for work:

  • in a protected resource area;
  • within the 100-foot buffer zone around certain resource areas; or
  • within the 200-foot riverfront area of a perennial stream or river (with smaller areas in some densely developed municipalities).

Many communities also have a local wetlands bylaw that’s stricter than state law, with larger buffers or no-disturbance zones.

The filings

  • Request for Determination of Applicability (RDA). Asks the Commission whether the Act applies to an area or project.
  • Notice of Intent (NOI). The full application for work subject to the Act. Resource area boundaries are typically delineated by a wetland scientist and shown on engineered plans.
  • Order of Conditions. The Commission’s permit, with conditions that run with the land until a Certificate of Compliance is issued.

Why it matters early

A wetland line can move a house, a driveway, or a septic system, and it can make a lot that looks buildable on a zoning map much harder to use. It’s worth confirming resource areas before design, not after.

General information, not legal advice.